The contract is for the renovation of the Hilltop Community Center, with a base bid amount of $10,053,131.00. The scope of work includes demolition, new construction, and renovations to various wings of the center, as well as site improvements. The project must be completed by December 31, 2026. The contract was awarded to Spaw Glass, with a total bid amount of $10,053,131.00 for the base bid and additional amounts for each additive. Some key aspects of the project include:
• Demolition of the existing spine corridor and preparation for a new serpentine walkway
• Major demolition and new construction renovations for Wing-A and Wing-C
• Minimal demolition and new construction renovations for Wing-E
• Exterior window replacements for Wing-B
• Addition of a canopy to the base bid's serpentine walkway
• Addition of an activity courtyard and native garden as site improvements
• Replacement of the existing HVAC system for Wing-F
The contractor is responsible for providing all necessary tools and equipment, removing and disposing of demolished materials and debris, and avoiding unnecessary noise and obstructions.