The Auburn Ravine Road at I-80 Improvement Project involves removing and replacing existing curb ramps, placing curb, sidewalk, and gutter, grinding existing asphalt concrete, and placing an HMA overlay, among other tasks. The project is located in Placer County, California, and the Engineer's Estimate for the project is $540,000. The project has a delayed start of 55 calendar days for the procurement of electrical materials and requires a one-year warranty. The contractor must possess a valid California Class A contractor's license or a combination of other licenses. The project is subject to state contract nondiscrimination and compliance requirements.
• The project involves various construction tasks, including removing and replacing existing curb ramps and placing curb, sidewalk, and gutter.
• The project has a delayed start of 55 calendar days for the procurement of electrical materials.
• The project requires a one-year warranty.
• The contractor must possess a valid California Class A contractor's license or a combination of other licenses.
• The project is subject to state contract nondiscrimination and compliance requirements.