This contract calls for the fabrication of two Remote Power Supply Unit (RPSU) modules for the villages of Port Heiden and Clarks Point in Alaska. The Alaska Energy Authority (AEA) issued a public competitive Invitation‑to‑Bid (ITB 19032) and ultimately awarded the contract to Weona Corporation. The scope is limited to steel structural fabrication, painting, and preparation of the modules for shipment; all site work, foundations, roofing, doors, windows, and mechanical/electrical systems are expressly excluded. Bids were required to be submitted in a sealed envelope by the extended deadline of December 5 2018, and the award is a lump‑sum, firm‑fixed‑price contract with no bid bond required. The vendor must provide documentation of at least three years of similar modular fabrication experience and maintain appropriate insurance, including naming the Denali Commission as an additional insured.
• Fabrication of two steel‑frame modules (Port Heiden – 13‑week lead time; Clarks Point – 16‑week lead time)
• Excludes site installation, foundations, roofing, doors/windows, and mechanical/electrical equipment
• Awarded to Weona Corporation on a lump‑sum basis; vendor must meet 3‑year experience and 5‑year staff expertise requirements.