The contract is for the installation of rubble rip-rap slope stabilization at six locations throughout the City of Palm Bay. The project involves the installation of rubble rip-rap around and in front of pipe ends, stabilization, turf mat, and sodding of all slopes. The contract was awarded to multiple vendors, with the grand total of the contract being $157,550.80. The key features of the contract include:
• The project consists of six locations throughout the City requiring installation of rubble rip-rap slope stabilization.
• The contract involves the installation of rubble rip-rap around and in front of pipe ends, stabilization, turf mat, and sodding of all slopes.
• The contract was awarded to multiple vendors, with the grand total of the contract being $157,550.80.
• The contract includes various items such as mobilization, maintenance of traffic, turbidity barrier, excavation and demolition, D-2 fabric, bedding stone, rip rap rubble, turf mat, and sod.