This solicitation calls for the demolition of the existing timber‑and‑steel pier that serves the Best Western Plus Coastline Inn, located in Wilmington’s Riverfront‑Riverwalk district. The work includes utility shutdown, removal of all structural elements, disposal of debris (including any hazardous material), installation of a new concrete pad, and site restoration with grading, back‑filling, and seeding. The City of Wilmington requires a minimum 14 % MWBE subcontracting effort and imposes strict safety, environmental, and erosion‑control measures. Payment is largely lump‑sum with an 80 % mobilization advance (capped at 5 % of the total contract) and progress payments based on a Schedule of Values. The contract term is 90 calendar days from the Notice to Proceed, with liquidated damages of $250 per day for overruns.
• Demolition of pier, removal of utilities, disposal of debris, and new concrete pad installation.
• MWBE subcontracting goal of 14 % of prime‑contract value.
• Fixed‑price (lump‑sum) payment structure, 90‑day performance window, $250/day liquidated damages.
• Strong environmental controls (turbidity curtains, EPA‑approved landfill disposal, asbestos/lead‑paint handling).
• Safety requirements include OSHA compliance, fire‑watch, and site fencing.