The contract is for the abandonment of old 30" / 33" trunk sewers in Omaha Street that have been replaced with other sewer mains in recent years and are no longer needed. The project involves the removal of these sewers and is estimated to cost around $80,000. The contract was awarded to three vendors: Mainline Contracting, RCS Construction, and Underground Constructions.
• The project is located in Rapid City, South Dakota
• The contract type is RFB (Request for Bid)
• The bid submission date was January 12, 2021
• The bid posting date was December 26, 2020
• The contract value is estimated to be around $80,000
• The vendors that were awarded the contract are Mainline Contracting, RCS Construction, and Underground Constructions