The City of Richland, Washington, requested sealed bids for the Columbia Playfield Playground Safety Surfacing Re-bid project. The project includes furnishing all materials, labor, tools, and equipment necessary to install poured-in-place safety surfacing of 5,196 square feet and other related requirements. The project is a federally funded CDBG project, and prevailing wages, including Davis Bacon wages, certified payroll, and all other applicable federal regulations shall be in force and effect. The engineer's estimate for the project is $95,000 - $115,000. Some key points about the project include:
• The project is a federally funded CDBG project.
• Prevailing wages, including Davis Bacon wages, certified payroll, and all other applicable federal regulations shall be in force and effect.
• The engineer's estimate for the project is $95,000 - $115,000.
• The project includes furnishing all materials, labor, tools, and equipment necessary to install poured-in-place safety surfacing of 5,196 square feet and other related requirements.
• The project has a time for completion of 90 calendar days from notice to proceed.
• Small, Minority, and Women-owned firms are encouraged to submit bids.