The MIRAMAR ROAD/KENT DRIVE STORM DRAIN IMPROVEMENT PROJECT involves the installation of approximately 875 lineal feet of storm drain pipe, 8 drainage inlets, 7 manholes, and appurtenant structures. The project also includes the removal and replacement of curb, gutter, and sidewalk, as well as the installation of sidewalk ramps. The estimated construction cost is $450,000, and a Class A General Engineering Contractor or Class "C-34" Pipeline Contractor license is required.
• The project is located in Sacramento, California.
• The bid was closed on April 27, 2017.
• The final award tabulation is available.
• The project is managed by the County of Sacramento - Construction.
• The point of contact for the project is Michael Cook.