The project involves the design, construction, and commissioning of Phase V of the Choctaw Point Container Terminal dock extension at the Port of Mobile, Alabama. The scope encompasses demolition of existing marine and landside structures, installation of new steel “Z” pile and concrete pile foundations, construction of a combination wall, crane‑rail system, fender and mooring hardware, extensive concrete work (piles, decks, paving), back‑land earthwork, utility installation (medium‑voltage switchgear, ductbanks, lighting), and related site‑cleanup. The contract is a competitive sealed‑bid, lump‑sum award with a performance bond equal to 100 % of the contract price and a liquidated‑damages clause of 0.033 % per day for late completion. The contract duration is 880 calendar days after receipt of the Notice to Proceed.