The City of Santa Ana is soliciting bids to widen Warner Avenue from four to six lanes between Oak Street and Grand Avenue, including demolition, utility relocation, new storm‑drain and water‑main installations, pavement reconstruction, sidewalks, curb ramps, bus pads, sound walls, traffic‑signal upgrades, street‑lighting, irrigation, landscaping, and off‑site improvements at Cherry Aerospace. The project also encompasses a separate protected bike‑lane component (Project 20‑6971). The contractor must hold a California Class “A” General Contractor license, provide a 10 % bid bond, and comply with prevailing‑wage, Community Workforce Agreement, and extensive documentation requirements.
• Roadway widening (4 → 6 lanes) with full asphalt and concrete pavement replacement.
• Utility work: relocation of water, sewer, storm‑drain, gas, electric, and installation of new fire‑hydrants and water‑meter boxes.
• Traffic‑signal, street‑light, sound‑wall, landscaping, irrigation, and bike‑lane construction.
• Mandatory DigAlert (811) notification 2 working days prior to any excavation; strict construction‑hour limits and temporary fencing constraints.