The Henry County Board of Commissioners is seeking bids for the construction of a hangar site at the Atlanta Speedway Airport. The project includes the furnishing of all labor, materials, equipment, and services required to fulfill the terms and conditions of the bid. The bid documents and specifications are available for inspection and download on the County's website. The project requires the contractor to provide all necessary materials, labor, and equipment to complete the construction of the hangar site. The contractor must also comply with all applicable rules and regulations of local, state, and national codes, laws, and ordinances. Some key features of the project include:
* Removal of existing headwall
* Stripping
* Unclassified excavation
* Embankment in-place
* Crushed aggregate base course
* Reinforced concrete band
* Red paint on header curb
* Yellow marking with microbicide and reflective media
* Temporary seeding
* Permanent seeding
* Remove and replace existing black vinyl coated chain link fence
* Remove and relocate underground electrical power services
* Remove and relocate underground fiber optic/communications services
* Water quality monitoring
* Recycled asphaltic concrete
* Prime coat
* Tack coat
* Concrete header curb
* No parking sign
* ADA accessible parking sign
* PVC sewer pipe
* Sanitary cleanout
* Sanitary sewer manhole
* Connect to existing sanitary manhole
* Sanitary sewer tap connection
* Water service
* Water main
* Fire hydrant assembly
* Connect to existing 8 water main
* 1 water meter
* Concrete pipe bollards
* Electrical conduit
* Mobilization
* Construction maintain and remove temporary construction exit
* Installation, maintenance, and removal of silt fence
* Installation, maintenance, and removal of temporary sediment trap
* Clearing and grubbing
* Temporary seeding
* Saw cut existing pavement
* Crushed aggregate base course
* Reinforced concrete paving
* Unclassified excavation
* Embankment in-place
* Permanent seeding
* Red paint on header curb
* White marking with microbicide
* Blue ADA marking with microbicide
The contractor must submit a bid price sheet that includes all the necessary items and quantities. The bid price sheet must be signed by an authorized representative of the contractor. The contractor must also submit a checklist for bid documents that includes all the required documents.