The City of Fayetteville seeks a qualified contractor to furnish, install, test, and commission a complete in‑ground hydraulic bus lift capable of handling 29‑ to 40‑ft heavy‑duty transit buses. The work includes civil excavation, concrete pit construction, installation of hydraulic equipment, electrical and control system integration, safety systems, liquid‑detection, fluid containment, and comprehensive testing and training. The contractor must also provide stamped engineering drawings derived from the lift manufacturer’s specifications, obtain all required permits, and coordinate utility relocations via change orders if needed. The project is funded with federal and local monies and is subject to Davis‑Bacon wage requirements, HUD‑4010 reporting, and various safety and environmental standards.
• Design, engineering, and stamped drawings for an in‑ground hydraulic lift (piston‑type, 60 000 lb capacity).
• Full civil work: excavation, reinforced concrete pit, shoring, drainage, and concrete finish (bare concrete acceptable).
• Installation of hydraulic system, control console (pedestal, no wireless), liquid‑detection, fluid‑containment, and 208 Y/120 V power supply.
• Permitting, utility relocation, environmental compliance (soil‑contamination data provided), testing, commissioning, and on‑site training.