The City of Sylvania is seeking bids for the Phase 2 phase of its Downtown Transportation Improvements project, which will reconstruct Main Street between Maplewood Avenue and Erie Street. The scope includes demolition, sub‑grade preparation, utility removal, pavement installation, streetscape elements, lighting, and related civil works. The engineer’s estimate is $4.62 million, with construction slated to begin July 1 2026 and finish April 15 2027. Bidders must submit a 10 % bid bond and comply with Ohio bid‑guarantee statutes.
• Demolition of existing pavement, curb, and utilities (≈ 3,200 SY pavement, 1,880 FT curb, 1,350 FT pipe, etc.)
• Installation of new concrete walks (various widths), sub‑grade compaction, geotextile, and asphalt paving
• Streetscape improvements including lighting, detectable warning surfaces, and maintenance bond (25 % of contract)
• Required submission of bid bond, affidavits, and prevailing‑wage documentation
• Project duration roughly 9 months with award anticipated May 18 2026.