The Illinois Toll Highway Authority (THA) is giving notice of its intent to amend its contract with Walsh Construction Company to provide for IL 38 Ramp Shoulder Material Change (Asphalt to Concrete) for work related to I-294 Interchange Reconstruction Cermak Plaza 35 to St. Charles. The original contract award amount was $326,995,971.35, and the cost of the extra work order/change order is $102,870.00.
• The change is germane to the original contract as signed.
• Provision for this work is included in the original contract.
• The contractor is Walsh Construction Company, located at 929 W. Adams Street, Chicago, IL 60607-3021.
• The NIGP code for this project is 912-00, which corresponds to Construction Services, General, including maintenance and repair services.