The U.S. Department of State is seeking a contractor to perform the consolidation and stabilization of historically significant underground tunnels at the Chief of Mission Residence (CMR) in Rome, Italy. The project involves furnishing and installing all materials required by the contract, and the Contractor shall complete the entire work ready for use not later than 115 calendar days after the date the Contractor receives the notice to proceed. The Contractor shall maintain discipline at the site and at all times take all reasonable precautions to prevent any unlawful, riotous, or disorderly conduct by or among those employed at the site.
Some key points to consider include:
• The Contractor shall commence work within 15 calendar days after the date the Contractor receives the notice to proceed.
• The Contractor shall complete the entire work ready for use not later than 115 calendar days after the date the Contractor receives the notice to proceed.
• A preconstruction conference will be held 10 days after contract award to discuss the schedule, submittals, notice to proceed, mobilization, and other important issues that affect construction progress.
• The Contractor shall provide an English-speaking supervisor on site at all times.
• The Contractor shall submit a detailed operational safety plan no later than 10 days before work starts.