The Jackson County Airport Authority is seeking bids for the Airfield Electrical Rehabilitation project at the Jackson County Airport in Jefferson, Georgia. The project involves furnishing all labor, equipment, and materials and performing all work in strict accordance with the plans and specifications. Prospective bidders should read the instructions carefully before submitting their bids. A non-mandatory prebid meeting will be held on February 10th, 2026, at 2:00 PM local time to discuss the project. The project has a DBE goal of 0.00% and requires compliance with various regulations, including Buy American Preferences and Davis-Bacon Act.
• The project requires a bidder's bond in the amount of 5% of the total amount of the proposal.
• A 100% performance bond and a 100% payment bond will be required of the contractor at the time of contract execution.
• The project must be completed within 60 calendar days from the issuance of the notice to proceed.
• Liquidated damages for delays in completion will be $500.00 per calendar day.
• Payment will be made monthly on completed work, with a maximum retainage of 10% of each progress payment.