The Saugus Union School District is seeking a qualified contractor to replace the existing asphalt hard‑courts at Bridgeport Elementary School, install new game striping, replace two ball‑walls with a third, and perform associated demolition, concrete curb work, and site preparation. The work is limited to the play‑court area on district property in Valencia, CA, and includes a mandatory pre‑bid site walk, pre‑qualification requirements, and strict compliance with California prevailing‑wage, insurance, and liquidated‑damage provisions.
• Scope: demolition of existing courts, new asphalt paving, game line striping, removal of two ball‑walls and installation of a third CMU wall, plus related concrete curb work.
• Requirements: $1 M pre‑qualification, 10 % bid bond, 100 % performance & payment bonds, prevailing‑wage compliance, DVBE 3 % participation, and a $2,500 per day liquidated‑damage clause.
• Schedule: Job walk April 15 2026, bid submission deadline May 5 2026, construction start June 15 2026, substantial completion July 29 2026, final close‑out July 31 2026.