This public‑competitive bid seeks a qualified contractor to rehabilitate the WWTP A sewer system along McNabb and Cline Streets in Lake Charles, LA. The work includes full‑depth pipe‑bursting replacement of 18‑in. HDPE pipe, manhole interior lining, temporary bypass pumping, and associated site work such as erosion control, traffic management, and final landscaping. The contract is a stipulated‑sum agreement with a 5 % bid bond and a 100 % performance bond, requiring a Louisiana contractor’s license (≥ $50 k). The project must be completed within roughly four months, with substantial completion in 80 calendar days and final completion in 125 days.