The Federal Bureau of Prisons seeks a contractor to refurbish the wastewater lift station at FCI Cumberland, MD. The work involves complete demolition of existing pumps, grinder, auger, electrical disconnects, and control systems, followed by installation of a new stainless‑steel NEMA 4X control panel with PLC/relay logic, VFDs, surge protection, and HOA switches. Additional tasks include installing a redundant level‑sensing system with audio/visual alarms, new grinder, auger, diverters, three wet‑well pumps plus three spares, upgraded grounding, conduit, and lightning protection, and full functional and hydrostatic testing. The contractor must also provide on‑site training (minimum six hours) and deliver as‑built documentation, O&M manuals, warranties, schematics, and PLC programming. Continuous sewage system operation must be maintained throughout, and all work must comply with federal, state, local, NEC, NFPA 820, OSHA, and FBOP security requirements. Quotes are due September 25, 2026 at 10 AM EST.
• Demolition and disposal of existing lift‑station equipment
• Installation of new stainless‑steel control panel with PLC/relay logic and VFDs
• Redundant level‑sensing system with audio/visual alarms
• New grinder, auger, diverters, three wet‑well pumps and three spare pumps
• Electrical upgrades: disconnects, ATS, grounding, surge/lightning protection
• Full functional, hydrostatic, and manufacturer startup testing
• Minimum 6 hours on‑site training and delivery of all as‑built documentation