This state‑funded project involves a comprehensive rehabilitation of adult living units and a full heating‑system upgrade within Building 62 of the Buffalo Psychiatric Center. The scope covers demolition, interior‑finish work, installation of new HVAC, plumbing, and electrical systems, and extensive coordination of floor drains, plumbing cores, wall‑tile, floor‑tile, ceiling tiles, and wall‑base details. The work is divided into four contract packages (Construction, HVAC, Plumbing, Electrical) and must comply with 2020 NYS Building, Mechanical, Plumbing, and Fire Codes, as well as specific behavioral‑health requirements such as ligature‑resistant hardware.
• Multiple addenda (01‑04) update specifications for door hardware, a wireless clock‑system, HVAC coil materials, and detailed finish‑legends.
• Estimated construction cost $3 M–$4 M; bid deposit $93,400; MBE/WBE goals 15% each, SDVOB 3%.
• Pre‑bid site visit scheduled for 5 May 2026 10:00 AM at the project site (400 Forest Ave., Buffalo, NY).