The Illinois Toll Highway Authority is giving its notice of intent to amend its contract with Judlau Contracting, Inc. to provide for Concrete Temperature Control for Winter Work for work related to I-490 Tollway Railroad Bridge Construction. The original contract award amount was $37,785,426.29, and the cost of the extra work order/change order is $176,943.88. The change is germane to the original contract as signed, and the additional efforts of this work are within the intent of the contract and Department policy.
• The Illinois Toll Highway Authority THA is amending its contract with Judlau Contracting, Inc.
• The amendment is for Concrete Temperature Control for Winter Work for the I-490 Tollway Railroad Bridge Construction.
• The original contract award amount was $37,785,426.29.
• The cost of the extra work order/change order is $176,943.88.
• The change is within the intent of the contract and Department policy.
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.