The Carl G. Washburne Memorial State Park Culvert Replacement Project involves replacing culverts at the park. The project includes mobilization, erosion control, demolition, excavation, and earthwork, among other tasks. The project is expected to start on August 1, 2026, and be substantially completed by September 15, 2026, with final completion by September 29, 2026. The project has a estimated cost range of $750,000 for bonding purposes.
• The project requires bidders to complete Attachment A, Form A-2 Pricing Form, and include it in their bid package submittal.
• The project has a liquidated damages clause of $1000 per calendar day for each day elapsed in excess of the substantial completion date.
• The project requires bidders to follow specific procedures for inadvertent discovery of human remains, including stopping work, securing and protecting the area, and notifying the project manager, agency official, Oregon State Police, State Historic Preservation Office, and Native American Tribes.
• The project requires bidders to follow a tree protection plan, which includes root protection, physical injury prevention, and soil compaction prevention.