This solicitation seeks a design‑build contractor to fully renovate the Pratt & Whitney elevated‑platform office area (B3001) on the second floor of Building 3001 at Tinker Air Force Base, Oklahoma. The work includes demolition of water‑damaged interior finishes, installation of fire‑rated walls, new acoustical ceilings, carpet, lighting, HVAC modifications, electrical rewiring, fire‑protection upgrades, and specialty equipment installation, all in compliance with DoD standards. The contractor must provide design submittals at 35 %, 65 %, 95 % and 100 % completion stages, manage hazardous‑material (asbestos/lead) abatement, and adhere to strict security and safety protocols.
• Interior demolition, new fire‑rated wall assemblies (STC 51), CAC‑50 acoustic ceiling, carpet and rubber‑floor stair finishes.
• Mechanical, electrical, and plumbing upgrades including new HVAC diffusers, power distribution, and lighting per UFC specifications.
• Fire‑protection system replacement (sprinklers, fire‑alarm, mass‑notification) and required testing, commissioning, and as‑built documentation.