This solicitation calls for the design‑build construction of water distribution, sanitary sewer, storm‑drainage, and associated paving works for the Westmoor Court Section 2 subdivision in Fort Bend County, Texas. The contractor will install PVC water mains, PVC sanitary sewer lines, large‑diameter reinforced concrete storm‑sewer pipes, numerous manholes, fire hydrants, valve boxes, concrete pavement, curbs, sidewalks, and related site‑development amenities, all within a fast‑track schedule of roughly four months. The project is overseen by the Fort Bend County Municipal Utility District No. 134C with LJA Engineering as the engineer of record. Competitive bids were received from eleven qualified firms, with total bid amounts ranging from about $2.93 M to $3.78 M.
• Install 6‑in and 8‑in PVC water mains, fire hydrants, and associated appurtenances.
• Construct 8‑in PVC sanitary sewer networks, multiple concrete manholes, and perform video inspection and back‑fill.
• Deploy reinforced‑concrete storm‑drainage pipes (24‑in to 66‑in) with cofferdam and de‑watering works.
• Provide reinforced‑concrete pavement, curbs, sidewalks, ADA ramps, and erosion‑control landscaping.
• Complete the work within a base construction period of 130 days (maximum 150 days).