The Illinois Toll Highway Authority (THA) is giving its notice of intent to amend its contract with F. H. Paschen, S.N. Nielsen to provide for BN 1653 - Pier 4 Cofferdam for work related to Roadway and Bridge Construction, IL390 and I-490 Interchange. The original contract award amount is $184,253,944.05, and the cost of extra work order/change order is $155,239.86.
* The contract is for construction services, general, including maintenance and repair services.
* The NIGP code for this contract is 912-00.
* The contractor is F.H. Paschen, S.N. Nielsen.
* The contract is not a small business set-aside procurement, but there is a BEP/VBP participation goal of 23.65% and 0.52%, respectively.