The Delaware River Joint Toll Bridge Commission is soliciting bids for the replacement of the pedestrian sidewalks on the Broad Street Viaduct at the Easton‑Phillipsburg Toll Bridge. The work includes demolition of existing concrete sidewalks and steel curb, installation of new concrete sidewalks with integral curbs, replacement of strip‑seal joints, structural steel repairs, drainage upgrades, protective fence and barrier removal/re‑installation, painting of steel members, and extensive electrical and fiber‑optic relocation for an electronic surveillance system. The contractor must be pre‑qualified by PennDOT or NJDOT, provide a 10 % bid security, secure performance and payment bonds, and meet a 25 % Identified Business Enterprise participation target.
• Demolition and reconstruction of 430‑ft steel plate‑girder viaduct sidewalks, including new concrete, curbs, and steel barriers.
• Structural steel repairs, painting, drainage scupper replacement, and installation of protective fencing.
• Relocation and installation of new electrical conduits, fiber‑optic lines, and surveillance system equipment; coordination with Norfolk Southern railroad and NJDOT highway occupancy permit.
• Mandatory compliance with pre‑qualification, IBE participation, traffic‑control coordination, and extensive safety/environmental provisions (lead‑based paint, containment, waste management).