Romoland School District is soliciting bids for the design‑build construction of a new parking lot and associated site improvements at Harvest Valley Elementary School in Menifee, California. The contract is a 56‑day, fixed‑price job valued roughly between $700 k and $800 k and includes earthwork, asphalt and concrete paving, curb & gutter, lighting, striping, drainage, utility relocation, irrigation, landscaping, chain‑link fencing, and limited electrical work for EV‑charging preparation. The project is subject to DSA approvals, California public‑works prevailing‑wage rules, and extensive safety, environmental, and warranty requirements.
• Mandatory pre‑bid conference and site walk on March 26, 2026 (must attend).
• Bid submission due April 22, 2026 2 PM; questions due April 8, 2026 3 PM.
• Contract time 56 calendar days, start approx. June 15, 2026, substantial completion by August 9, 2026.
• Requires Class A/B contractor license, 5 % retainage, $100 k unforeseen‑conditions allowance, performance and payment bonds, and compliance with prevailing‑wage and fingerprinting requirements.