The City of Archer is seeking a qualified design‑build team to deliver Phase One (approximately 8‑inch, 42,000‑ft force main) and Phase Two (interconnection, lift‑station integration, SCADA, odor control, railroad crossing coordination) of the Archer‑Newberry wastewater interconnect on an accelerated schedule. The contract requires complete design, permitting, construction, testing, as‑built documentation, and grant‑closeout support, with a firm construction completion deadline of September 30, 2026.
• Design‑build scope includes engineering, utility coordination, right‑of‑way acquisition, construction of an 8‑inch force main (~42 000 LF) and associated appurtenances.
• Phase Two adds lift‑station upgrades, electrical/SCADA integration, odor‑control systems, and railroad crossing work; the City may direct‑purchase long‑lead equipment.
• The project must meet federal, state, and local grant requirements (2 CFR Part 200, Build America/Buy America, DEP, ARPA) and include a guaranteed completion date with liquidated‑damage provisions.