The City of Waco is seeking bids for the replacement of the Dissolved Air Flotation Water Treatment Plant Pump No. 2 VFD. The project includes the furnishing of all labor, materials, equipment, appurtenances, and incidentals required for demolition, removal, and disposal work to properly install the equipment and ensure all instrument and control connections are correctly configured. The project requires all site work, labor, equipment, and materials to be complete and in place as stated in the RFB, shown on the plans, and specified herein. Key features of the project include:
* Replacement of the existing VFD with a new one that meets the specifications outlined in the RFB
* Installation of all necessary components to deliver a fully integrated and operational system
* Compliance with the 2023 National Electric Code and City of Waco Permitting and Inspection requirements
* Performance of functioning testing before commissioning the VFD
* Completion of all site work, labor, equipment, and materials within 285 calendar days
* Substantial completion and in-service within 255 calendar days
* General Contractor to self-perform a minimum of 51% of the project
* Liquidation fee of $1000.00 for each day of delay
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.