The City of Fresno is soliciting bids for a pavement‑rehabilitation project on approximately 0.5 mi of Shaw Avenue, from Fruit Avenue to West Avenue. The work includes milling, asphalt overlay, ADA‑compliant curb‑ramp reconstruction, utility adjustments, signage and striping updates, and traffic‑loop replacement, all to be completed within an 80‑working‑day schedule. The contract is funded with federal aid and carries standard public‑work bonding, licensing, and prevailing‑wage requirements.
• Scope: 0.3 ft milling, 0.34 ft HMA overlay, ADA curb‑ramps, manhole/valve adjustments, new signage/striping, traffic‑loop upgrades.
• Budget: Construction allocation of $1,653,427 (maximum).
• Schedule: 80 working days from Notice to Proceed; liquidated damages $1,500 per day for delays.
• Requirements: Valid CA Class A or C‑12 contractor license, 10 % bid deposit, 100 % payment & performance bonds, compliance with Davis‑Bacon prevailing‑wage, Buy‑America, SWPPP, and CMIS reporting.