The purpose of this project is to upgrade and modify the low voltage electrical and lighting systems at Eielson's Central Heat Power Plant (CHPP) to include removal, and replacement of the existing electrical panels, associated transformers, and the remainder of existing outdated lighting fixtures within CHPP facility at Eielson AFB. The project requires the contractor to perform the work within 545 calendar days after receiving the notice to proceed. The contractor must also comply with various Federal Acquisition Regulation (FAR) clauses and Defense Federal Acquisition Regulation Supplement (DFARS) clauses. The project has a magnitude of between $1M and $5M, and the NAICS code is 238210 with a Small Business Size Standard of $19M.
• The project involves upgrading and modifying low voltage electrical and lighting systems at CHPP.
• The contractor must remove and replace existing electrical panels, associated transformers, and outdated lighting fixtures.
• The project has a duration of 545 calendar days.
• The contractor must comply with various FAR and DFARS clauses.
• The project has a magnitude of between $1M and $5M.
• The NAICS code is 238210 with a Small Business Size Standard of $19M.