The Town of Westminster is seeking bids from paving contractors for the 2026 paving project, which includes milling, shimming, and overlays, as well as structure adjustment where necessary. The project is expected to start on June 1, 2026, and be completed by September 1, 2026. The contractor will be responsible for all work, including mobilization, tack coat emulsion, traffic control, compaction testing, and cold joint milling. The town reserves the right to add or subtract from the scope of work at its sole discretion.
• The project includes 27,000 SY of asphalt milling and 3,100 TON of asphalt pavement.
• The contractor must use the most current VTRANS approved mix design for the Type II-50 Blow Marshall Bituminous Concrete Pavement.
• The contractor must provide compaction equipment and operators capable of attaining a compacted density of at least 92.5% and 96.5% of the mix’s maximum specific gravity.
• The contractor must maintain temporary crosswalk markings throughout the duration of the project.
• The project shall be conducted so that the original road profile is maintained.