The project involves the replacement of a boardwalk at O’Leno State Park. The boardwalk requires piles with a design compression load of 8 kips, and the contractor will be responsible for determining the installed length to achieve the required capacity. The total number of piles indicated in the plans is twelve. The project is being managed by the Department of Environmental Protection (DEP), and bids are being accepted until December 16, 2025.
• The project requires the replacement of a boardwalk at O’Leno State Park.
• The boardwalk design includes piles with a 2 7/8” diameter and a 10/12 design.
• The contractor will be responsible for determining the installed length to achieve the required capacity.
• The total number of piles indicated in the plans is twelve.
• The project is being managed by the Department of Environmental Protection (DEP).
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.