This RFQ solicits qualified construction‑management‑at‑risk (CM‑AR) firms to lead the comprehensive renovation of Robinswood Middle School in Orlando, FL. The project involves full‑scope renovation of the campus, including demolition, new construction, life‑safety upgrades, accessibility improvements, and temporary facilities to maintain school operations during construction. The anticipated schedule spans design services beginning December 2025, pre‑construction services in May 2026, a notice to proceed in June 2027, and substantial completion by June 2029, with an estimated construction cost of $68.5 million. The solicitation is awarded, but the vendor details are not disclosed in the available record.
• Scope covers demolition, new building construction, system upgrades, and phasing to keep the school occupied.
• Project budget: $68,510,000.
• Timeline: design (Dec 2025), pre‑construction (May 2026), construction (June 2027‑June 2029).