The City of Goodyear has awarded a contract to CORE Construction, Inc. for the design and construction of the Goodyear Police Department Building Phase II. The contract includes pre-construction and construction services, with a guaranteed maximum price (GMP) proposal to be developed by the contractor. The project involves the construction of a new police department building, with the City providing the design and the contractor responsible for the construction. The contract includes provisions for constructability and bidability reviews, as well as a waiver of subrogation. The contractor is required to provide a construction management plan, project schedule, and cost estimates, and to attend project team meetings. The contract also includes provisions for insurance, bonds, and indemnification. The key aspects of this contract include the scope of work, the GMP proposal, and the requirements for the contractor's performance.
* The scope of work includes pre-construction and construction services for the Goodyear Police Department Building Phase II.
* The GMP proposal will be developed by the contractor based on the design provided by the City.
* The contractor is required to provide a construction management plan, project schedule, and cost estimates.
* The contractor must attend project team meetings and provide progress updates.
* The contract includes provisions for insurance, bonds, and indemnification.
* The contractor is responsible for the construction of the police department building.
* The City is responsible for providing the design and overseeing the project.
* The contract has a duration of 496 days and is renewable.
* The contract value is estimated to be $18,272,001.