The City of Madison is reconstructing the parking lot at Hoyt Park, a public‑works project that includes demolition of existing pavement and curbs, earthwork, base preparation, new asphalt paving, concrete curbing, sidewalk installation, storm‑water drainage improvements, gate replacement, erosion‑control measures, and landscaping/seedings. The prime contractor, Parisi Construction, LLC, will manage a $381,188.68 lump‑sum contract, mobilize on 27 Apr 2026, and complete the work within a 75‑day construction window, targeting final completion by 30 Aug 2026. Key contractual requirements include a 5 % bid bond, SBE participation goals, compliance with City of Madison Standard Specifications, tree‑protection provisions, and weekly erosion‑control inspections.
• Scope: demolition, grading, base course, asphalt, concrete curbs/gutters, sidewalks, gate, storm‑water pipe, erosion control, landscaping.
• Schedule: start 27 Apr 2026, finish 30 Aug 2026 (75 days of work).
• Financials: $381,188.68 lump‑sum; 5 % bid bond; SBE goal of 20 % of base bid value.