The City of Tucson awarded a contract to MMI Tank and Industrial Services for the Manzanita Tank Lining and Recoating project. The contract involves the lining and recoating of the Manzanita tank, with a base bid price of $543,518. The project is expected to be completed within 335 consecutive calendar days. The contract includes provisions for liquidated damages, guarantee, and assignment. The contractor is required to provide performance and payment bonds, as well as insurance coverage. The contract also includes a good faith effort clause to utilize small business enterprises (SBEs). Key aspects of the contract include:
• Project scope: Lining and recoating of the Manzanita tank
• Base bid price: $543,518
• Completion time: 335 consecutive calendar days
• Liquidated damages: $600/day for each day the work remains incomplete after the scheduled completion date
• Guarantee: The contractor shall guarantee all work against defects of material and workmanship for a period of two years
• Assignment: Neither party shall assign the agreement or sublet it as a whole without the written consent of the other
• Insurance: The contractor shall provide insurance coverage, including commercial general liability and workers' compensation
• Good faith effort: The contractor shall make a good faith effort to utilize SBEs in the performance of the contract