The contract is a university‑issued Request for Proposal to fully renovate three research laboratories within the C.S. Mott building at Wayne State University, covering demolition, structural modifications, HVAC, plumbing, electrical, laboratory casework, finishes, and associated commissioning. The scope includes compliance with Michigan prevailing‑wage rules, detailed safety and environmental requirements, and a strict schedule that mandates substantial completion by June 6 2025. The award was made to D&S Contractors, who must submit a lump‑sum bid, provide required bonds, and adhere to the university’s wage, insurance, and reporting policies.
• Full‑scope general‑contractor work: demolition, trades, lab‑specific casework, MEP systems, finishes.
• Mandatory pre‑bid meeting (Jan 23 2025) and site visit (Jan 30 2025); bid deadline Feb 7 2025.