The contract is for general construction services for the City of Goodyear's Municipal Complex tenant improvement projects, specifically the Wellness Center. The contract includes a time extension and a change order for additional construction activities. The scope of work includes demolition, hazardous material testing, and construction of the project. The contract value is estimated to be around $498,633. The contract is a fixed-price contract with a duration of 238 days. The City of Goodyear is the agency responsible for the contract, and Foresite Design & Construction, Inc. is the vendor awarded the contract.
• The contract includes a time extension to November 11, 2023, to allow for additional construction activities.
• The contract includes a change order for $35,322.37 for the demolition of the north half of Building D.
• The contract includes a cost estimate for the proposed early demolition of the north half of Building D.
• The contract includes a milestone schedule for the project.
• The contract includes a list of clarifications and exclusions for the project, including the use of existing water and power sources, the exclusion of certain systems, and the inclusion of allowances for hazardous material survey and other costs.