This contract calls for the complete demolition of a damaged brick‑framed structure at 1652 Wexford Street, Mobile, AL, including utility disconnections, debris removal, erosion and sediment control, and site restoration. The City of Mobile’s Municipal Enforcement Department issued a sealed‑envelope RFQ on March 3 2022, with quotes due by March 10 2022. The contract will be awarded to the lowest responsive, responsible bidder (AA&A DEMOLITION) on a stipulated‑sum basis, and work must be completed within 15 calendar days of a written Notice to Proceed. Liquidated damages of $250 per day apply for delays beyond the substantial‑completion deadline. All required documentation, insurance, E‑Verify proof, and a published notice of final completion are mandatory for final payment.
• Wet demolition of the structure, footings, slabs, and all associated masonry.
• Utility capping, complete debris haul‑away, temporary and permanent erosion control, and site seeding.
• Strict timelines (15‑day work window) and liquidated‑damage clause ($250/day).