This contract involves the modification of the draft‑tube assembly for Unit B‑8 at the Rock Island Hydroelectric Powerhouse owned by Chelan Public Utility District. The scope includes constructing a cofferdam, dewatering the turbine area, surveying and mapping sidewalls, drilling and installing anchors, placing reinforcing steel, forming and pouring concrete, and finishing/grouting to achieve a new hydraulic profile consistent with existing units. The work is a specialist civil‑hydro construction effort that mirrors prior modifications on Units B‑5, B‑6, B‑7, and B‑9. The contract was awarded to J.F. Brennan Company, Inc. for $1,537,000.
• Primary activity: Cofferdam construction, dewatering, concrete work, and hydraulic profile modification of a hydro‑electric draft tube.
• Location: Rock Island Powerhouse, Chelan County, Washington (Chelan Public Utility District).
• Awarded vendor: J.F. Brennan Company, Inc. (single‑award, lump‑sum value $1.537 M).
• Solicitation details: Labor & Materials solicitation (Solicitation Number 24‑13700) published May 6 2025, bid opening June 10 2025.