The City of Rexburg awarded a municipal sewer‑line contract (Project WW‑01‑24) to Edstrom Construction, Inc. for the construction of a new 8‑inch sanitary gravity‑sewer main from Sunrise Drive to University Blvd., including manhole installation, trenching, back‑fill, road and sidewalk repairs, and related utility coordination. The bid was opened on June 4 2024, with a bid security of at least 5 % of the total bid. The contract requires performance and payment bonds equal to 100 % of the contract price, a 5 % retainage on each payment, and liquidated damages of $500 per day for any delay beyond the 60‑day substantial‑completion deadline. The work must comply with Idaho public‑works standards, OSHA safety requirements, and local traffic‑control plans.