The contract is for the rehabilitation of approximately 2,220 feet of road reconstruction on West Boulevard from Flormann Street to Saint Patrick Street. The project includes the installation of approximately 4,405 linear feet of under-drain. The engineer's estimate for the project is $621,000.00, and the lowest bidder is Western Construction with a base bid of $542,359.00.
• The project includes road reconstruction and under-drain installation.
• The engineer's estimate for the project is $621,000.00.
• The lowest bidder is Western Construction with a base bid of $542,359.00.
• The contract was awarded through a competitive bidding process.
• The City of Rapid City is the agency responsible for the project.