This contract is for the repair of the Salinas Dam Access Road, Santa Margarita Truck Trail, and V-Notch Weird Access Road. The project includes road reconstruction, slope repairs, and other related work. The engineer's estimate for the project is $326,885. The contract was awarded through a formal bid process, and the bidders included several engineering and construction companies. The scope of work includes roadway excavation, imported borrow, hydroseeding, and concreted rock slope protection, among other tasks.
• Road reconstruction and slope repairs
• Access to Salinas Dam equipment locations
• Operational and maintenance access for County staff
• Engineer's estimate: $326,885
• Formal bid process
• Multiple bidders
• Various scope of work tasks