The Outagamie County Dog Park contract is a lump‑sum, design‑build construction project for a new municipal dog park in Appleton, WI. The scope includes site demolition, earthwork, grading, erosion‑control, utility installation (water, sanitary, storm), pavement (asphalt and concrete), lighting, fencing, shade structures, a prefabricated restroom building, landscaping, and associated site furnishings. The award was made to Relyco Plus for $1,494,052, with a bid deadline of May 27 2025 and a required substantial completion by April 10 2026 (final completion by April 20 2026). The contract follows AIA A101/A201 standard forms, includes required insurance, performance bonds, and liquidated damages of $250 per day for late substantial completion.
• Scope: demolition, grading, utilities, paving, lighting, fencing, shade structures, restroom building, landscaping, site furnishings.
• Schedule: start May 6 2025, substantial completion April 10 2026, final completion April 20 2026.
• Financials: award value $1.49 M, 5 % bid bond, performance bond equal to contract sum, $250/day liquidated damages.