The City of Worcester is undertaking a multi‑phase redevelopment of Lincoln Square, which includes demolition of an existing World War I memorial, site grading, new monument installation, extensive park improvements, utility upgrades, and related construction work. The contract is a sealed‑bid, lowest‑responsible‑bid award that was won by F.W. Madigan for a total contract sum of approximately $5.08 million. The project is scheduled in three phases: Phase 1 (demolition and site prep) must be completed within 90 days of the notice‑to‑proceed; Phase 2 runs through 31 Mar 2026 and covers the reconstruction of the monument and related amenities; Phase 3 continues from 1 Apr 2026 to 1 May 2027, completing the park and infrastructure enhancements. Key contractual requirements include a 5 % bid security, performance and payment bonds for the full contract amount, prevailing‑wage compliance, detailed MWBE labor reporting, strict noise‑control hours, and extensive weekly reporting (payroll, progress, and photographic documentation).