The City of Vancouver, Department of Public Works, has awarded a contract to Rotschy, Inc. for the Water Station 5 Reservoirs and Pump Station project. The contract involves the construction of two new 4-million gallon AWWA/ANSI D110 Type I concrete reservoirs, a new pump station, and various site improvements. The contract also includes phased demolition of the existing reservoirs and pump station. The work must be completed by December 31, 2023, with a revised contract amount of $25,607,999.18.
• The contract includes multiple change orders, with the latest being Change Order No. 16, which adds a 15-inch long 30-inch PExFLG DIP spool for the R02 reservoir overflow riser section.
• The contract has a lump sum price of $6,115.56 for the change order work.
• The contract has undergone several revisions, with the latest revised contract amount being $25,607,999.18.
• The contract has a completion milestone date of May 22, 2024.