The City of Madison Board of Public Works is procuring the design‑build construction of the South Point Public Works Facility, a municipal infrastructure project budgeted at up to $46 million. Three pre‑qualified contractors submitted competitive bids, with the lowest total bid ($41.08 M) from J. H. Findorff & Son Inc. The contract is slated to start mid‑September 2026, with award approval expected by the Common Council on 20 Oct 2026.
• Project type: Facilities construction for a public‑works building.
• Budget ceiling: $46 M (engineering estimate and construction budget).
• Procurement method: Full and open competition with pre‑qualification ID 426; lowest‑total‑price award anticipated.
• Key dates: Bid due 27 Aug 2026, bid opening 24 Sep 2026, award 20 Oct 2026, start 15 Sep 2026.
• Vendors: J. H. Findorff & Son Inc. (lowest bid), JP Cullen & Sons, Inc., Corporate Contractors Inc. (higher bids).