The Quint Street Bridge Replacement project involves the removal and demolition of a double track railroad bridge and the reconstruction of an elevated earthen berm in its place. The project requires the maintenance of daily rail traffic and must be completed within a single 31-hour rail service outage. The contract was awarded to Shimmick Construction Company Inc. with a bid price of $4,450,000. The key aspects of the project include:
• Bridge removal and demolition
• Reconstruction of an elevated earthen berm
• Maintenance of daily rail traffic
• Completion within a single 31-hour rail service outage
• Installation of 2000 track feet of concrete ties during weekend single track outages
• Removal of a single span of the Jerrold Avenue Bridge during a single seven-hour rail service outage