The contract is for the 2015-16 Neighborhood Traffic Management Projects-Phase 2, which includes the furnishing of all labor, materials, and equipment for doing all the work associated with placing conventional asphalt concrete, and associated markings and roadside signs for speed bumps, speed bumps with cut outs, speed tables and a raised crosswalk. The estimated cost of the project is $300,000.00. The contract was awarded to Biondi Paving, with a bid amount of $257,736.00.
• The project includes the installation of speed bumps, speed tables, and raised crosswalks.
• The project requires the furnishing of all labor, materials, and equipment.
• The estimated cost of the project is $300,000.00.
• The contract was awarded to Biondi Paving, with a bid amount of $257,736.00.